[Solved] NUR3045 Unit 2 Assignment 2

Project Management Techniques Health Information Management Systems

Instructions

The factors for planning a successful EHR implementation are below including each activity’s duration and predecessor(s):

  • Activity- A. Create the EHR vision
    • Duration (days)- 5
    • Predecessor- none
  • Activity- B. Identify the planning horizon
    • Duration (days)- 10
    • Predecessor- A
  • Activity- C. Obtain buy-in from affected parties
    • Duration (days)- 30
    • Predecessor- B
  • Activity- D. Develop a financing and acquisition strategy
    • Duration (days)- 10
    • Predecessor- C
  • Activity- E. Develop functional, data, and technical strategies
    • Duration (days)- 45
    • Predecessor- C
  • Activity- F. Conduct vendor selection
    • Duration (days)- 45
    • Predecessor- D, E
  • Activity- G. Plan the EHR implementation
    • Duration (days)- 15
    • Predecessor- C, E, F
  • Activity- H. Conduct benefits realization study
    • Duration (days)- 10
    • Predecessor- A-G

Use the factors listed above to:

  1. Create the PERT chart for this implementation
  2. Indicate the critical path on the PERT chart
  3. Design the GANTT chart for this implementation

Solution

The above Information can be given as Activity Description Duration Predecessor A Create EHR Vision 5 Nil B Identify Planning Horizon 10 A C Obtain buy in from affected parties 30 B D Develop Financial……………………………………To access the rest of the solution for $10, please click on the purchase button