Project Management Techniques Health Information Management Systems
Instructions
The factors for planning a successful EHR implementation are below including each activity’s duration and predecessor(s):
- Activity- A. Create the EHR vision
- Duration (days)- 5
- Predecessor- none
- Activity- B. Identify the planning horizon
- Duration (days)- 10
- Predecessor- A
- Activity- C. Obtain buy-in from affected parties
- Duration (days)- 30
- Predecessor- B
- Activity- D. Develop a financing and acquisition strategy
- Duration (days)- 10
- Predecessor- C
- Activity- E. Develop functional, data, and technical strategies
- Duration (days)- 45
- Predecessor- C
- Activity- F. Conduct vendor selection
- Duration (days)- 45
- Predecessor- D, E
- Activity- G. Plan the EHR implementation
- Duration (days)- 15
- Predecessor- C, E, F
- Activity- H. Conduct benefits realization study
- Duration (days)- 10
- Predecessor- A-G
Use the factors listed above to:
- Create the PERT chart for this implementation
- Indicate the critical path on the PERT chart
- Design the GANTT chart for this implementation
Solution
The above Information can be given as Activity Description Duration Predecessor A Create EHR Vision 5 Nil B Identify Planning Horizon 10 A C Obtain buy in from affected parties 30 B D Develop Financial……………………………………To access the rest of the solution for $10, please click on the purchase button